|  
                   
                
                MIL-STD-1553B DATA BUS HARNESS TESTER  
                                                                        
                - CP300 HT  
                				  
                                  Description:  
                                  Compupower Private Limited has developed the  CP300 HT Harness Tester, a low cost, light weight and portable instrument to  test the faults in any MIL-STD-1553B Network with ease and High level of  confidence.   
                                  All measurements are Pass/Fail type tests with  proper LED indications. By means of five push-to-test switches, tester can  detect shorts, opens, shorts to shield and phase reversal (cross over) on the  Bus and Stubs. 
                                  The main feature of this Tester is that, these  tests can be performed from the LRU/RT ends of the Stub cables because, access  to the Couplers and Main Bus itself may be difficult. 
                                  Features: 
                                  
                                    - Easy to use hand held battery operated equipment 
 
                                    - Low cost, light weight and easy to use by  single person 
 
                                    - Fast and easy testing with Go/No-Go LED  indicators 
 
                                    - Required no Main Bus disconnection 
 
                                    - Detects shorts and opens in the Stubs and in the  Main Bus from Stub ports 
 
                                    - Detects shorts to shield in the Bus and Stubs from  the Stub ports
 
                                    - Detects open, short or incorrect value terminators  from the Stub ports
 
                                    - Detects crossovers/phasing errors
 
                                    - Simple validation procedure
 
                                    - Increased battery life by way of push-to-test feature  of the Tester Base Unit
 
                                   
                                  The CP300 HT consists of two units, 
                                        (1)   Base unit (CP300 HTB) 
        (2)   Remote unit or Transmitter (CP300 HTR)    
                                  Base unit is used for Stub - shield continuity,  Stub continuity check, Bus termination check and Bus-shield continuity  tests.  Both Base unit and Remote unit  are used for Phase reversal/crossover test.   Both the units are battery powered and work with standard  batteries.   The battery life is  increased by way of push-to-test feature of the tester Base unit, and by  keeping the Remote unit in ‘Idle mode’ when not actually being interrogated by  the Base unit for Phase reversal check.  
                                  The following faults can occur in a 1553B network  because of crushed cables, failed connector joints or human error. 
                                  
                                    - Stub/Bus  side open.
 
                                    - Stub/Bus  side short.
 
                                    - Shorts  to shield on the Bus and on the Stubs.
 
                                    - Phase  reversal (Swapping of high and low wires resulting in phase   change).
 
                                    - Terminators  open/short or sometimes wrong value terminators.
 
                                   
                                  Sequence of  tests: 
                                  The following test sequence should be followed  during tests. 
                                              1.  Stub-shield short. 
              2.  Stub continuity (DC resistance) 
              3.  Bus Termination. 
              4.  Bus-shield short. 
              5.  Phase reversal/cross over.  
                                  Operation:  
                                  There are five push-to-test switches (buttons)  to carry out the tests.  Tests can be  carried out by pressing the appropriate PTT’s (push-to-test switches).   The particular PTT (S1-S5) should be pressed  for approximately three seconds to allow the (test) circuit to stabilize to its  final value.   It  is   necessary for this equipment   (Tester)  to  carry   out  the tests  in   the  sequence  S1-S5 for unambiguous Pass/Fail result. The  operation of the five PTT’s S1-S5 are defined below. 
                                  Stub to Shield Continuity: 
                                  This test is basically a DC insulation  resistance test.   The resistance between  any conductor and shield less than 50KW  is interpreted as  lead-to-shield short and is indicated by Pass (Green)/Fail (Red) LED. 
                                  Stub continuity Check:     
                                       This test checks for the DC continuity of  the stubs.  If the DC resistance of the  Stub is below 1W ±10%, it is  interpreted as Stub short and is indicated by a Red LED.   If the resistance is above 5W ±10%,  it is interpreted as Stub open and is also indicated by another Red LED.  If the resistance is between 1-5W ±10%,  it is interpreted as Normal condition and is  indicated by a Green LED.  
                                  Bus Termination check: 
                                       This function checks for shorts, opens on  the Bus conductors.  It can test for  short, open or wrong termination from a Stub port.  The results of the test are indicated by  three LEDs.  
                                  Note: In  case   of wrong  termination  it   is  assumed  that   only  two  types   of terminators are possible in a 1553B network (i.e. 78W and  3000W)   the  Pass/Fail criterion is  differentiated between these two terminators only, even though the  specifications   of   MIL-STD-1553B  states   that the  normal termination is  70-85W nominal.     The Tester is capable of differentiating wrong termination values below  50W as short and above 110W  as open. 
                                  Bus to shield Continuity: 
                                        This test checks for any shorts from the Bus  HI or Bus LO conductor to shield on the Bus cable.  This test is carried out form the Stub  (Access to Bus is not required).  The  Pass/Fail is indicated by Green / Red LEDs respectively. 
                                  Phase Reversal Check:  
                                        This test is carried out by using both Base  unit and Remote unit.  Base unit is  connected to one Stub cable and the Remote unit connected to another Stub cable  which has passed the tests S1-S4.  This  test determines if there are any phase reversals of the conductors between  Remote unit and Base unit of the Tester as explained in the example given  below.  The Pass/Fail is indicated by  Green/Red LEDs respectively.  
                  Example:  
                                  In  a 1553B network of 10 Stubs, if the Remote unit is connected to any one of the  Stubs, say Stub1 which passed tests (S1-S4), and the Phase reversal test is  carried out by Base unit from Stub2 through 10 with respect to Stub1, where  Remote unit is connected.   The following  conditions should be analyzed to ascertain the location of the fault. 
                                  1.  No Phase reversal:  If the Base unit indicates Pass throughout  all the Stubs with respect to the Stub where Remote unit is connected.  
                                  2.  Phase reversal:  If the Base unit indicates Fail in one or few  Stub locations with respect to the Remote unit, then the Phase reversal is on  those Stub(s) where the Base unit shows Fail (Red) LED indication.   
                                  If the Base unit indicates Fail indication on  all the Stubs with respect to the Remote unit, then the Phase reversal is on  the Stub where the Remote unit is connected.  
                                  Note1: If any failure is detected any where in the sequence S1-S5, user should not  proceed to the next test(s) in the sequence without rectifying that particular  fault in the network, without that, it can lead to ambiguous or incorrect  results.  (Eg.: when Bus short (S3 fail)  and Bus shield short (S4 fail) exist, S4 test will show Green giving misleading  result).   
                                      Note2: The patch cords used for testing should not have any break connectors in  between.  
                    
                  Test sequence flow chart: 
                  
                    
                  Specifications: 
                  
                     
                      | LED Indication: | 
                        | 
                     
                     
                      STUB-SHLD 
                        CONTINUITY | 
                      GREEN = PASS 
                        RED = FAIL | 
                     
                     
                      STUB 
                        CONTINUITY | 
                      RED = OPEN (>5Ω) 
                        GREEN = NORMAL (1-5Ω) 
                        RED = SHORT (<1Ω) | 
                     
                     
                      BUS 
                        TERMINATION | 
                      RED = OPEN /WRONG (>110Ω) 
                        GREEN = NORMAL (50-110Ω) 
                        RED = SHORT (<50Ω) | 
                     
                     
                      BUS-SHLD 
                        CONTINUITY | 
                      GREEN = PASS 
                        RED = FAIL | 
                     
                     
                      | PHASE REVERSAL | 
                      GREEN = PASS 
                        RED = FAIL | 
                     
                     
                      | BATTERY LOW | 
                      RED (Base Unit, <6.2V) 
                        FLASHING RED (Remote unit <5.4V) | 
                     
                   
                  Current Ratings: 
                  
                     
                      | Base Unit | 
                      75mA max. | 
                     
                     
                      | Remote Unit | 
                      ≤5mA (Without Transmission)  ≤20mA (With 
                        Transmission) | 
                     
                     
                      | Test Method | 
                      Push- to-test | 
                     
                     
                      | Batteries | 
                      Standard 9V Alkaline or Rechargeable Ni-Cad. | 
                     
                     
                      | Battery charger | 
                      Input 230VAC, 50Hz. | 
                     
                     
                      | Charging time | 
                      6-8 Hours | 
                     
                     
                      | Connector | 
                      BJ 77 (Trompeter) | 
                     
                     
                      | Storage Temp. | 
                      0°C to 50°C | 
                     
                     
                      | Operating Temp. | 
                      10°C to 50°C | 
                     
                     
                      | Size | 
                      Base unit : (196 X 100 X 40)mm 
                        Remote unit : (157 X 84 X 30)mm | 
                     
                     
                      | Accessories (supplied) | 
                      
                          - Harness Tester validation Jig,
 
                            Model: CP 300HTV 
                          - Two patch cords with PL 75 at both ends
 
                          - Ni-cad multi cell charger
 
                          | 
                     
                    |